Hammersmith Flyover to Fully Reopen 'Well Ahead' of Olympics

TfL promises no more daytime closures for repairs after games

Participate

TfL and Boris Accused of Reneging on Congestion Promises

Could The Westway be Next to Close?

Hammersmith Flyover Reopens

Hammersmith Flyover Faces Possible Closure

Sign up for a free newsletter from ChiswickW4.com

Get the Hammersmith newsletter

Register for the Fulham Newsletter

Work to repair Hammersmith Flyover is on track to be completed well ahead of the Olympic Games according to Transport for London (TfL) although no specific date has been given for full reopening.

They say that the repairs will ensure the flyover remains in use for many decades countering fears that the structure would need to be totally rebuilt after the Olympics.

The first new tensioning cables are to be installed during coming months with diamond cutting being used to remove the existing concrete.

Work to strengthen the five weakest spans of the 16 span structure will be completed ahead of the 2012 Games, ensuring that the flyover can carry full traffic loading during the Games. Afterwards, TfL will return to the structure to strengthen the remaining spans. This work however will not require further weight restrictions to be imposed and TfL hope to complete it with only off peak lane closures, causing much less disruption than is presently the case.

The works, which began in January, have seen around 200m of the central reservation along the flyover removed in preparation for new cables which will support the structure. Using a number of specialist techniques including hydrodemolition and diamond cutting, around 140 tonnes of concrete have been removed by using both high pressurised water and a rotating cord impregnated with diamonds to cut the material away. These techniques meant that work could be carried out safely while traffic continued to use the flyover.

TfL say that a team of engineers are working 24 hours a day, seven days a week to complete the work, often in a crawl space far less than human height. Now the key enabling works have been completed, they will begin to install a new concrete base, drainage and tailored anchorages for the new cables within the structure. The design for the new post-tensioning system will see new cables installed above and below the bridge deck inside a specially made duct, which will supplement the load capacity of the remaining cables.

The new ducts will then be filled with a wax oil to prevent deterioration from any water ingress, as well as enable the cables to be easily replaced as and when required.

Isabel Dedring, Deputy Mayor for Transport, said: “Our team are well aware of the major impact these works have in west London for road users and local people. That is why the engineers are working twenty four hours a day to get the job done. They are making good progress but while the restrictions are in place we will continue to have dedicated staff monitoring and managing the impact on traffic every hour of the day.”

Although work is progressing well, TfL continues to advise motorists that due to the flyover not being fully open, they should consider avoiding the area if at all possible. Signage and traffic management measures continue to be in place to help reinforce this to drivers across West London.




March 7, 2012