Forthcoming Roadworks in Brentford

Traffic delays likely in the local area due to lane and road closures

Forthcoming Roadworks in Brentford

Participate

Traffic and Travel in Brentford

Sign up for our Brentford newsletter

Comment on this story on the

Ealing Park Gardens
04 August — 11 August
Severe delays likely - Road closure
Works location: Ealing Park Gardens from Windmill Road to o/s No3 Ealing Park Gardens
Works description : Microsurfacing works, dates and duration to change following PAA
Responsibility for works: Ealing
Current status: Planned work about to start
Works reference:  DV00665000894

Baronsmede
05 August — 12 August
Severe delays likely - Road closure
Works location: Baronsmede from Popes Lane to Gunnersbury Lane
Works description : Resurfacing works, dates and duration to change following PAA
Responsibility for works: Ealing
Current status: Planned work about to start
Works reference:  DV00665000946

Wood Lane, Isleworth
10 August — 12 August
Severe delays likely - Road closure
Works location: Wood Lane level crossing
Works description : LIFT & CHANGE RAILS ON THE DOWN ROAD AT LEVEL CROSSING
Responsibility for works: Network Rail
Current status: Planned work about to start
Works reference:  KL156HOU-11-70-100820

Lionel Road South, Brentford
10 August — 12 August
Delays likely - Lane closure
Works location: 70m from the Stop Line of the junction with Great West Road
Works description : 25/039 tel0255425 - slot cut c/w sensor loops to repair traffic signals SD4 plus feed to existing chamber (f/w 2m new duct and underkerb) 10.00-15.00, northbound c/w swapping lane 1 & 2and f/w to chamber (ped access maintained)
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG516S000000006257

St Marys Crescent
11 August — 13 August
Severe delays likely - Road closure
Works location: THORNBURY RD TO RIDGEWAY RD N
Works description : Pothole pledge
Responsibility for works: Hounslow
Current status: Planned work about to start
Works reference:  FQ00888823125

Boston Manor Road
13 August — 17 August
Delays possible - Some carriageway incursion
Works location: OPP 155
Works description : OSV Locate <33mm Fway in Footway. Our intention is to complete
the Permanent Reinstatement in the same phase
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference:  MU301000031493917-001

Balfour Road
10 August — 12 August
Delays possible - Some carriageway incursion
Works location: 13 BALFOUR ROAD, LONDON, W13 9TN
Works description : B Box Repair in Footway. Our intention is to complete the PermanentReinstatement in the same phase
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference:  MU301000031493280-001

A315 High Street, Brentford
27 Jul - 21 Aug
Delays likely - Traffic lights,
Works description : TRAFFIC LIGHTS ASSOCIATED WITH WORKS ON LONDON ROAD
Responsibility for works: Thames Water
Current status: Advanced planning
Works reference:  MU031J415-CROSSCON-002

B455 South Ealing Road, Ealing
18 May — 06 September
Delays possible - Some carriageway incursion
Works description : IMGA202378 - MAINS REPLACEMENT WORKS. REPLACING APPROX 1109M X CI ANDREPLACING WITH 630MM PE BY MEANS OF INSERTION. THIS WILL ALSO INCLUDE REPLACEMENT AND TRANSFER OF SERVICES
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference:  AZ0071000917934

A205,A315 Kew Road
14 Feb — 2 October
Delays likely - Lane closure
Works description : Cycle Superhighway 9 - initial notice for section 58 purposes and to cover works before/after construction is complete and prior to full opening while other phases are being completed.
Responsibility for works: Transport for London
Current status: Work in progress
Works reference:  YG65200000074

August 11, 2020

Bookmark and Share