A4001,A3002 Boston Road, Hanwell |
13 June — 14 June |
Delays likely Traffic control (multi-way signals) |
Works description: Excavate & connect to CGL/SGN Gas Main providing gas supply to new housing development. Approx dimensions: 2mx 0.5m footway, 1m x 0.5m carriageway. Depth: 0.8m. |
Responsibility for works: E S Pipelines Ltd |
Current status: Planned work about to start |
Works reference: ZY013F1643/EPLR |
|
A315 London Road, Isleworth |
12 June — 14 June |
Delays possible Some carriageway incursion |
Works description: B Box Install <33mm Cway in Carriageway. Our intention is tocomplete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031280172-001 |
|
A4,A3002 Boston Manor Road, Brentford |
14 June — 18 June |
Delays possible Some carriageway incursion |
Works description: Service Pipe Repair in Footway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031295755-001 |
|
A4,A3002 Boston Manor Road, Brentford, Hounslow |
14 June — 18 June |
Delays possible Some carriageway incursion |
Works description: Service Pipe Repair in Footway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031295893-001 |
|
B455 South Ealing Road, Ealing, Ealing |
12 June — 25 June |
Delays possible Some carriageway incursion |
Works description: IMGA202336. Trial Holes and potential camera survey of both LP andMPmainto give further information for our upcoming replacementworks. |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000840055 |
|
A310 Twickenham Road, Isleworth, Hounslow |
14 June — 18 June |
Delays unlikely No carriageway incursion |
Works description: BUILD F/W8 |
Responsibility for works: VIRGIN MEDIA |
Current status: Planned work about to start |
Works reference: NK100/SSEMBU/100289266 |
|
A315 Chiswick High Road, Chiswick |
13 June — 14 June |
Delays unlikely No carriageway incursion |
Works description: Remedial works to correct defect, we need to place an infill cover on the jf4 |
Responsibility for works: Openreach |
Current status: Planned work about to start |
Works reference: BC006TI001LC500276507000 |
|
A315 London Road, Brentford, Hounslow |
12 June — 13 June |
Delays unlikely No carriageway incursion |
Works description: CLEAR BLOCKAGE IN FOOTWAY |
Responsibility for works: VIRGIN MEDIA |
Current status: Planned work about to start |
Works reference: NK100/SSSMRE/100289348 |
|
A4001,A3002 Boston Road, Hanwell, Ealing |
12 June — 14 June |
Delays unlikely No carriageway incursion |
Works description: CUSTOMER SIDE LEAKAGE SUPPLY PIPE REPLACEMENT |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU356002141HXKS--000001 |
|
B4491 Popes Lane, Ealing, Ealing |
12 June — 25 June |
Delays unlikely No carriageway incursion |
Works description: TO PROVIDE A NEW SERVICE TO A SIGN POST WORKS FOR ROAD PURPOSES |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV806S000000001047 |
|
B455 South Ealing Road, Chiswick |
12 June — 20 June |
Delays unlikely Some carriageway incursion |
Works description: EXCAVATE JOINT HOLE AND SMALL TRENCH FOR NEW 3PHSE LV DOMESTIC SUPPLY BACKFILL AND REINSTATE |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Planned work about to start |
Works reference: LP551S30003102 |
|
Baronsmede, Ealing, Ealing |
12 June — 25 June |
Delays unlikely No carriageway incursion |
Works description: TO PROVIDE 1 X NEW SERVICE TO A SIGN POST WORKS FOR ROAD PURPOSES |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV806S000000001045 |
|
Brentwick Gardens, Brentford, Hounslow |
12 June — 14 June |
Delays unlikely Some carriageway incursion |
Works description: Service Pipe Repair <33mm in Footway. Our intention is to completethe Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031297670-001 |
|
Canberra Road, West Ealing, Ealing |
13 June — 19 June |
Delays unlikely Some carriageway incursion |
Works description: This permit is for Thames Water to store spoil only while we carry out connection works for 77-83 Broadway |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808800000045 |
|
Clayton Crescent, Brentford, Hounslow |
14 June — 18 June |
Delays unlikely Some carriageway incursion |
Works description: Service Pipe Repair <33mm Fway in Footway. Our intention is tocomplete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031299279-001 |
|
Cranmer Avenue, West Ealing |
12 June — 14 June |
Delays unlikely No carriageway incursion |
Works description: CUSTOMER SIDE LEAKAGE SUPPLY PIPE REPLACEMENT |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU356002141JDCP--000001 |
|
Disraeli Road, Ealing |
14 June — 18 June |
Delays unlikely No carriageway incursion |
Works description: CUSTOMER SIDE LEAKAGE SUPPLY PIPE REPLACEMENT |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU356002141JFKH--000001 |
|
Dorset Road, Ealing |
13 June — 17 June |
Delays unlikely Some carriageway incursion |
Works description: Boundary Box Exchange Fway in Footway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031297395-001 |
|
Enfield Road, Acton |
12 June — 14 June |
Delays unlikely Some carriageway incursion |
Works description: Valve Repack 0 to 6" in Carriageway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031297404-001 |
|
Grove Park Road, Chiswick |
13 June — 17 June |
Delays unlikely Some carriageway incursion |
Works description: Serv Pipe Relay Ex Fitting in Footway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031286949-001 |
|
Gunnersbury Drive, Ealing |
12 June — 25 June |
Delays unlikely No carriageway incursion |
Works description: TO PROVIDE 2 X NEW SERVICES TO SIGN POSTS. WORKS FOR ROAD PURPOSES |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV806S000000001050 |
|
Lion Gate Gardens, Richmond |
14 June — 17 June |
Delays unlikely Some carriageway incursion |
Works description: Demolish 1 existing jointbox(s) or cabinet base(s) |
Responsibility for works: Openreach |
Current status: Planned work about to start |
Works reference: BC006TI001LC500272884302 |
|
Mattock Lane, West Ealing |
14 June — 17 June |
Delays unlikely No carriageway incursion |
Works description: Installation of new feeder pillar |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG426412492 |
|
Melbourne Avenue, West Ealing |
13 June — 19 June |
Delays unlikely No carriageway incursion |
Works description: NHH Plot 1 , 1x25mm MDPE mtrd Supply IN in Footway. Our intention is tocomplete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808800000045-001 |
|
Midhurst Road, West Ealing |
13 June — 17 June |
Delays unlikely Some carriageway incursion |
Works description: B Box Exchange <33mm Fway in Footway. Our intention is to completethe Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031294257-001 |
|
Montague Road, Hanwell |
12 June — 14 June |
Delays unlikely Some carriageway incursion |
Works description: Ferrule Exchange Cway in Carriageway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031216737-001 |
|
Northcroft Road, West Ealing |
12 June — 14 June |
Delays unlikely No carriageway incursion |
Works description: CUSTOMER SIDE LEAKAGE SUPPLY PIPE REPLACEMENT |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU356002141HSQW--000002 |
|
Plum Garth, Brentford |
13 June — 17 June |
Delays unlikely Some carriageway incursion |
Works description: Chamber Adjust Sml Frame & Cover Fway in Footway. Our intention isto complete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031297406-001 |
|
Plum Garth, Brentford |
14 June — 18 June |
Delays unlikely Some carriageway incursion |
Works description: Service Pipe Repair <33mm Fway in Footway. Our intention is tocomplete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031299381-001 |
|
Riverview Grove, Chiswick |
12 June — 14 June |
Delays unlikely Some carriageway incursion |
Works description: Service Pipe Repair in Footway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031289907-001 |
|
St Margarets Road, Hanwell |
13 June — 19 June |
Delays unlikely Traffic control (give & take) |
Works description: Disconnection of supply in fw and in Carriageway. Our intention is tocomplete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808272800315-001 |
|
Waldeck Road, Chiswick |
12 June — 18 June |
Delays unlikely Traffic control (give & take) |
Works description: new water supply. HH Plot 1, 1x50mm MDPE mtrd Supply. works in footwayand in Carriageway. Our intention is to complete the PermanentReinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808735800045-001 |
|
Warwick Road, Ealing |
12 June — 14 June |
Delays unlikely Some carriageway incursion |
Works description: Serv Pipe Relay Ex Fitting fway and in Carriageway. Our intention is tocomplete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031213903-001 |
|