'Safety Critical' Maintenance Requires Closure of A316
Night time work will mean road is shut from Chalkers Corner (5-22 May)
A315,A205 Kew Bridge Road, Brentford
01 May — 22 May
Delays likely - Lane closure
Works description: CS9 - segregated cycleway construction
Responsibility for works: Transport for London
Current status: Advanced planning
Works reference: YG65200000108
A406 Gunnersbury Avenue (north Circular Road)
11 May — 14 May
Delays likely - Lane closure
Works description : Related to NationalGrid London Power Tunnels 1 Decommission Project. Decommission of Thermocouple Pit 13 within verge and Decommission of Linkbox 59/60 within Verge/FW
Responsibility for works: NATIONAL GRID ELECTRICITY TRANSMISSION
Current status: Planned work about to start
Works reference: HP003OCULPT1721015 |
A315 High Street, Brentford
12 May — 14 May
Delays likely - Traffic control (multi-way signals)
Works description : SEWER CLEANING - PLANNED
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU026002141PGNH--000001
B455 South Ealing Road, Ealing
13 May — 15 May
Delays likely - Traffic control (two-way signals)
Works description : Remedial Works Following Defect Inspection- To rectify remedial work in Carriageway
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference: AZ0071000900369
Boston Manor Road, Brentford
13 May — 15 May
Delays likely - Traffic control (multi-way signals)
Works description : BUILD NEW CHAMBER IN THE C/W- WORKING ON BEHALF OF COLT
Responsibility for works: CITY OF LONDON TELECOMMS
Current status: Planned work about to start
Works reference: CS02020/05/016